Webb Road resurfacing to begin Nov. 17 in Dothan

The City of Dothan says resurfacing Webb Road between North Range Street and Ross Clark Circle is scheduled to begin November 17 and take two to three weeks.

By Dothan Local Staff
Ask AI

Summarize this page with

ChatGPTClaudePerplexityGoogle AI
Editorial illustration: Webb Road resurfacing to begin Nov. 17 in Dothan

In short

  • The City of Dothan says a contractor will resurface Webb Road from North Range Street to Ross Clark Circle, beginning Tuesday, November 17, with th...
  • According to the city’s November 13 announcement, Lewis Inc. will start by milling the existing pavement on November 17.
  • Resurfacing is scheduled to begin the following week, on November 23.

The City of Dothan says a contractor will resurface Webb Road from North Range Street to Ross Clark Circle, beginning Tuesday, November 17, with the work expected to take two to three weeks.

According to the city’s November 13 announcement, Lewis Inc. will start by milling the existing pavement on November 17. Resurfacing is scheduled to begin the following week, on November 23.

The city says traffic will be shifted through the work area, with pilot cars and flaggers guiding motorists. Construction will be sequenced to minimize traffic impacts near Carver Ninth Grade Academy as much as possible, according to the announcement.

The city asks motorists to seek alternate routes and use caution while traveling in the area. For more information, the announcement directs residents to contact the Public Works Department at 334-615-4420.

Know someone who should see this?

Ask AI

Summarize this page with

ChatGPTClaudePerplexityGoogle AI

Also in Dothan

Your town, every weekday morning

What’s on today, new local guides and stories, in one short free email.

Free. Unsubscribe any time.